Jun 04

Phase 1 of Lovettsville Community Center Construction is Complete

Posted on June 4, 2020 at 10:00 AM by Heidi Kellum

Work initiated at the end of March to finish the geothermal wells and parking lot for the Lovettsville Community Center has been completed. Phase 1 of the original construction schedule is now complete, including the sediment basin, riser structure, pond access road, fencing, and the temporary access road connecting East Broad Way to the gravel parking lot. 

Due to the termination of the construction contract in January 2020, the remaining phases of construction of the new community center are delayed until a contractor can be procured. Preparations for the contractor bidding process are underway.

Construction is estimated to resume in late 2020.

For more information about the Lovettsville Community Center project, visit the project page.

Mar 30

Loudoun County to Complete Lovettsville Community Center Parking Lot

Posted on March 30, 2020 at 9:32 AM by Heidi Kellum

On March 30, weather permitting, work is scheduled to begin at the Lovettsville Community Center project site to complete parking lot construction, earthwork and geothermal piping. This construction work will take approximately two months. 

Although the county is taking steps to finish projects in the area around the existing community center, construction for the new Lovettsville Community Center is delayed as the county works towards procuring a contractor, estimated for late 2020.

For more information about the Lovettsville Community Center project, visit the project page.
Jan 15

Construction is Delayed for the New Lovettsville Community Center

Posted on January 15, 2020 at 3:49 PM by Heidi Kellum

Loudoun County has issued a notice of termination for the construction contract for the Lovettsville Community Center project effective January 17, 2020. Work on the Lovettsville Community Center will be delayed while the county seeks a new contractor, which is expected to take six to seven months, to complete the remaining construction.

In the coming weeks, the area surrounding the construction site will be emptied of equipment and the County will complete work to secure the site for the duration of the delay. Construction for the project could be delayed up to 12 months.

Construction of the community center is expected to resume by the end of 2020. 


For more information about the Lovettsville Community Center project, visit the project page.