Mar 30

Loudoun County to Complete Lovettsville Community Center Parking Lot

Posted on March 30, 2020 at 9:32 AM by Heidi Kellum

On March 30, weather permitting, work is scheduled to begin at the Lovettsville Community Center project site to complete parking lot construction, earthwork and geothermal piping. This construction work will take approximately two months. 

Although the county is taking steps to finish projects in the area around the existing community center, construction for the new Lovettsville Community Center is delayed as the county works towards procuring a contractor, estimated for late 2020.

For more information about the Lovettsville Community Center project, visit the project page.
Jan 15

Construction is Delayed for the New Lovettsville Community Center

Posted on January 15, 2020 at 3:49 PM by Heidi Kellum

Loudoun County has issued a notice of termination for the construction contract for the Lovettsville Community Center project effective January 17, 2020. Work on the Lovettsville Community Center will be delayed while the county seeks a new contractor, which is expected to take six to seven months, to complete the remaining construction.

In the coming weeks, the area surrounding the construction site will be emptied of equipment and the County will complete work to secure the site for the duration of the delay. Construction for the project could be delayed up to 12 months.

Construction of the community center is expected to resume by the end of 2020. 


For more information about the Lovettsville Community Center project, visit the project page.
Dec 11

Work to Complete Phase 1 of the Lovettsville Community Center Project Continues

Posted on December 11, 2019 at 2:19 PM by Heidi Kellum

In December, work to complete Phase 1 of the Lovettsville Community Center project continues with the completion of the gravel parking lot and the geothermal well field.

Meridian Construction Co., Inc., Loudoun County's subcontractor, has completed drilling for the geothermal wells and is now working to connect the wells to the geothermal vault, and to backfill where needed. Grading and gravel placement for the parking lot is expected to be complete by the end of the month. 


For more information about this project, visit the Lovettsville Community Center project page.