Sterling Boulevard and W&OD Trail Overpass

Overview

  • This project provides for the design, and construction of a W&OD pedestrian/bike bridge over Sterling Boulevard (Route 846). 
  • When complete, the pedestrian/bike bridge will separate pedestrians, bicyclists, horseback riders, and other users of the W&OD Trail from roadway traffic on Sterling Boulevard removing the current at-grade crossing at Sterling Boulevard.
  • Funding sources for this project include general obligation bonds, cash proffers and local tax funding. 
  • This project is currently in the design phase. Construction will follow the completion for the design phase and ROW activities, currently projected to be fall 2023.

Current Phase: Design - 100% Plans

Estimated Timeline

  • Fall 2020 - Spring 2023: Design
  • Summer 2023 - Spring 2024: Right of Way
  • Summer 2024: Utilities Relocation 
  • Fall 2023 - Winter 2024: Procurement of Construction Contractor
  • Winter 2024: Award Contract – Construction
  • Spring 2024: Notice to Proceed – Construction
  • Spring 2024 - Spring 2026: Construction
  • Spring 2026: Substantial Completion

Stay Informed About This Project

 Related Documents

Contact Us

Media Inquiries